What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? Normal Time (days) 6 Immediate Predecessor(s) Normal Cost 8 Activity Design Wiring Chip install Software Testing Crash Time (days) 5 6 3 3 5 Crash Cost $1,000 400 600 1,200 1,600 $900 300 500 900 1,000 4 5 8 A, B с The minimum cost of crashing the following project by 4 days is $| (enter your response as a whole number).